Excavation calculator

Enter the footing size, depth and number of pits. You get the earthwork in m³, cft and brass, the loose soil after bulking, the number of tractor or tipper trips, and the digging cost.

m³, cft and brassSoil bulking and truck tripsRuns in your browser
Use the footing size from your drawing. For a trench, enter its length, width and depth with 1 as the number.
Added to every side of the footing. IS 1200 uses 600 mm where workers need room for formwork.
Ordinary earth swells 20% to 30% once dug.
Digging rate
Machine digging in ordinary soil, about ₹5 per cft (₹500 per brass). Typical, edit to your quote.
Change any value and the result updates instantly.
0
m³ to dig
Size of each pit dug0
Excavation (in place)0 cft
In brass (100 cft)0
Loose soil after bulking0 m³
Trips to carry it away0
Digging cost₹0
Advertisement

How to use the excavation calculator

  1. Choose metres or feet and enter the length, width and depth of one footing pit, and how many such pits there are. For a wall trench, enter the trench size and 1 as the number.
  2. Enter the working space on each side. This is extra width dug around the footing so workers can fix formwork and place concrete.
  3. Pick the soil. The bulking figure fills in, and you can change it.
  4. Pick the vehicle that will carry the soil away, or enter its loose capacity in cft.
  5. Enter the digging rate per cft or per brass from your contractor's quote.

How it is calculated

Pit dug = (L + 2 × working space) × (W + 2 × working space) × depth
Excavation = pit dug × number of pits
Loose volume = excavation × (1 + bulking % ÷ 100)
Trips = loose volume (cft) ÷ load per trip, rounded up
1 m³ = 35.3147 cft   ·   1 brass = 100 cft

Earthwork is measured and paid on the hole, not on the heap. IS 1200 Part 1, the Indian standard for measuring earthwork, says excavation is measured "without allowance for increase in bulk". Once dug, soil loosens and takes more room, so the heap and the number of truck trips are worked out on the loose volume.

Working space follows IS 1200 as well. Where working space is authorised and nothing else is specified, it allows 600 mm from the face of the footing. This calculator starts at 300 mm, half the IS 1200 figure, as a lighter default for shallow house footings. Type 0.6 if your engineer specifies it.

Bulking figures are the middle of Engineering ToolBox's ranges: earth 20% to 30% (25% used), loam 15% to 25% (20%), clay 20% to 40% (30%), sand and gravel 20% to 30% (25%), wet gravel with clay 50% to 60% (55%), and rock 40% to 80% (60%).

Advertisement

Worked example

Twelve footings of 1.5 × 1.5 m, dug 1.5 m deep, with 0.3 m of working space on each side, in ordinary soil, carried away by tractor trolley, at ₹5 per cft.

  • Each pit = (1.5 + 0.6) × (1.5 + 0.6) × 1.5 = 2.1 × 2.1 × 1.5 = 6.615 m³.
  • Excavation = 6.615 × 12 = 79.38 m³ = 79.38 × 35.3147 = 2,803 cft = 28.03 brass.
  • Loose soil = 79.38 × 1.25 = 99.23 m³, or 3,504 cft.
  • Tractor trips = 3,504 ÷ 100 = 35.04, so 36 trips.
  • Digging cost = 2,803 × ₹5 = ₹14,016.

Some of that soil goes back as backfill around the footings once they are cast, so you may not need to cart all of it away. Keep what you need on site and send only the rest.

Excavation in India: brass, trucks and rates (2026)

Brass. In western India, sand and earth are often counted in brass. Maharashtra's 2025 sand policy, for example, gives housing-scheme beneficiaries five brass of sand free. One brass is 100 cft, or 2.83 m³. A tractor trolley with a load bed of 8 × 5 × 2.5 ft holds exactly 100 cft, which is why a trolley load is called a brass.

VehicleLoose loadBasis
Tractor trolley100 cft (1 brass)8 × 5 × 2.5 ft load bed
Small tipper3 m³ (about 106 cft)Tata 610 SK, 3 m³ body, 4 t payload
10-wheel tipper10.5 m³ (about 371 cft)Tata Signa 1923.K, 10.5 or 12 m³ box body

Wet soil is heavy, so a small tipper may reach its weight limit before its body is full. Ask the transporter what load they actually carry.

Rates. As of November 2026, InfraLens's rate analysis for machine excavation by JCB, including a 50 m lead, is ₹163 to ₹177 per m³ for Ahmedabad. That is about ₹4.60 to ₹5.00 per cft, or ₹460 to ₹500 per brass. Tata Hitachi gives a wider ₹80 to ₹300 per m³ for basic soil, and hard rock costs much more. The default of ₹5 per cft is typical, edit to your quote. The InfraLens rate covers only a 50 m lead, so carting soil off the site is extra.

Before you dig

  • Get the footing sizes and depth from the structural drawing, not from a neighbour's house. Soil differs from plot to plot.
  • Agree with the contractor whether the rate is on the pit volume or on trips. A trip carries loose soil, which takes about a quarter more room than the pit it came from in ordinary earth.
  • Plan where the heap will sit. At 25% bulking, 80 m³ of pits becomes about 100 m³ of loose soil.

Once the pits are dug, the concrete calculator gives cement, sand and aggregate for the PCC bed and footings. The house construction cost calculator shows foundation work in the context of the whole budget.

Common questions

How do you calculate excavation for a footing?

Add the working space to each side of the footing, then multiply length × width × depth. A 1.5 × 1.5 m footing with 0.3 m working space on each side, dug 1.5 m deep, is 2.1 × 2.1 × 1.5 = 6.615 m³. Multiply by the number of similar footings for the total.

How many cft are in 1 brass?

1 brass is 100 cubic feet, which is about 2.83 m³. A tractor trolley with an 8 × 5 × 2.5 ft load bed holds exactly 1 brass.

What is the bulking or swell factor of soil?

Dug soil takes more room than it did in the ground. Ordinary earth and sand swell 20% to 30%, clay 20% to 40% and broken rock 40% to 80%, according to Engineering ToolBox. So 10 m³ of pit in ordinary soil makes about 12.5 m³ of loose soil to carry away.

Is excavation paid on the pit volume or the loose volume?

On the pit volume. IS 1200 Part 1 measures excavation without any allowance for increase in bulk. Truck trips, on the other hand, carry loose soil, so you need more trips than the pit volume alone suggests.

What is the JCB excavation rate per brass in 2026?

InfraLens's rate analysis for machine excavation in Ahmedabad is ₹163 to ₹177 per m³ including a 50 m lead, which is about ₹460 to ₹500 per brass. Hard soil, rock, water in the pit and carting away cost extra. Treat any rate as a starting point and get a written quote.

How much working space should be left around a footing?

IS 1200 allows 600 mm from the face of the footing where working space is needed and nothing else is specified. Deep pits, wet soil and pits needing shoring need more. Your engineer decides what is needed for your site.

Sources

Made in Surat by WiserFool, the studio of Khanjan Kavani, architect and contractor. Formulas are tested against published references before a tool goes live. Last reviewed 24 November 2026. How we build and check tools.