Enter the size of your slab, footing or column, or its volume, and pick the grade. You get the cement bags, the sand and aggregate in m³, cft and brass, the water, and the material cost.
Next step
How to use the concrete calculator
- Pick the member: slab, footing, column, beam or a plain PCC bed. The labels change to match, for example a column asks for its two sides and its height.
- Enter the length and width in feet or metres, and the thickness or height in inches, feet, mm or metres. For several identical members, such as 6 footings, enter the number. If you already know the volume, switch to "Volume directly" and type it in m³ or cft.
- Choose the grade. M20 (1:1.5:3) is the usual choice for a house slab, beam and column. M10 and M15 are for PCC under footings and floors. Use "Custom ratio" for any other mix, such as 1:4:8.
- Check the water–cement ratio and the rates for cement, sand and aggregate. The rates are typical Surat figures. Typical, edit to your quote.
- Read the cement bags, sand and aggregate in m³, cft and brass, the water, and the material cost. Everything updates as you type.
How it is calculated
Dry volume = wet volume × 1.54
Each material = dry volume × its part ÷ sum of parts
Cement bags = cement m³ × 1,440 ÷ 50
Water (litres) = cement kg × water–cement ratio
Wet concrete takes up less space than the loose cement, sand and aggregate that go into it, because the fine particles fill the gaps between the stones and the mix is compacted. Site engineers allow for this by multiplying the wet volume by 1.54. Brick&Bolt and The Constructor both use 1.54. Brick&Bolt calls it a common site estimation rule, not a design standard.
Other assumptions, all stated so you can check them:
- Cement weighs 1,440 kg per m³ (IS 875 Part 1), so one 50 kg bag is 0.0347 m³.
- Dry loose sand and aggregate are taken at 1,600 kg per m³ to convert m³ into tonnes. IS 875 Part 1 gives 1,540 to 1,600 for dry sand and 1,600 to 1,870 for broken stone. Wet sand is heavier, so a truck of damp sand holds fewer m³ per tonne.
- 1 m³ = 35.3147 cft, and 1 brass = 100 cft.
- The material cost uses the exact quantity. "Bags to buy" rounds cement up to whole bags.
- Wastage is not added. Add 2% to 5% for spillage if you are ordering for a whole house.
Worked example
A roof slab of 20 ft × 15 ft, 5 inches thick, in M20 (1:1.5:3). These are the calculator's default inputs.
- Wet volume = 20 × 15 × 5 ÷ 12 = 125 cft, which is 3.540 m³.
- Dry volume = 125 × 1.54 = 192.5 cft. The parts add up to 1 + 1.5 + 3 = 5.5.
- Cement = 192.5 ÷ 5.5 = 35 cft = 0.991 m³. At 1,440 kg per m³ that is 1,427 kg, or 28.54 bags. Buy 29 bags.
- Sand = 192.5 × 1.5 ÷ 5.5 = 52.5 cft, about 0.53 brass or 1.49 m³ (2.38 tonnes).
- Aggregate = 192.5 × 3 ÷ 5.5 = 105 cft, about 1.05 brass or 2.97 m³ (4.76 tonnes).
- Water at a ratio of 0.5 = 1,427 × 0.5 = 714 litres.
- Cost at ₹400 a bag, ₹1,300 a tonne of sand and ₹1,100 a tonne of aggregate: cement ₹11,417, sand ₹3,092, aggregate ₹5,233. The total is ₹19,743, because each line is rounded separately. That is ₹5,578 per m³ of concrete, before labour, mixer, vibrator and shuttering.
As a check, Brick&Bolt's own example for 1 m³ of M20 gives 8 bags of cement, 0.42 m³ of sand and 0.84 m³ of aggregate. Switch to "Volume directly", enter 1 m³ and the tool shows 8.06 bags, 0.42 and 0.84.
Nominal mixes, IS 456 and Surat prices
IS 456:2000, clause 9.3, allows nominal mix concrete only for M20 and lower grades. Its Table 9 caps the water at 34 kg per 50 kg bag of cement for M10, 32 kg for M15 and 30 kg for M20, which is a water–cement ratio of 0.68, 0.64 and 0.60. Keep below those limits. UltraTech lists M25 as a design mix with no fixed ratio. The 1:1:2 option here is a site rule of thumb, so the calculator warns you when you pick it. For M25 and above, ask for a design mix to IS 10262 or order ready-mix concrete.
Default rates, as of November 2026. Typical, edit to your quote:
| Material | Default | What the sources show |
|---|---|---|
| Cement, 50 kg bag | ₹400 | Surat, May 2026: PPC ₹387, OPC 43 ₹407, OPC 53 ₹423 (InfraLens). The all-India average rose ₹7 to ₹356 in September 2026, and the West rose ₹9, with more increases expected (Construction World). |
| Sand, per tonne | ₹1,300 | Surat dealer listings on 24 November 2026 range from ₹650 to ₹2,350, most between ₹1,000 and ₹1,500 (IndiaMART). InfraLens gives ₹2,354 for river sand and ₹1,570 for M-sand. |
| 20 mm aggregate, per tonne | ₹1,100 | Surat listings ₹900 to ₹1,300 on 24 November 2026 (IndiaMART). InfraLens gives ₹1,458. |
In Surat, sand and kapchi (aggregate) are usually sold by the tonne, so the calculator gives tonnes as well as m³, cft and brass. If your supplier quotes per brass, divide the brass rate by the tonnes in a brass. That is about 4.5 tonnes at 1,600 kg per m³. Gujarat doubled the royalty on sand from ₹40 to ₹80 per tonne in July 2025, and the trade expected material prices to rise as a result.
Steel costs about as much as the concrete materials in a slab. At 80 kg per m³ and ₹65 a kg, the 3.54 m³ slab above needs about 283 kg of steel, roughly ₹18,400. Work out the bars in the steel calculator. For the whole house, start with the house construction cost calculator, and work out pit volumes with the excavation calculator before you price the PCC under each footing.
Tips before you pour
- Measure batches by box, not by shovel. A wooden farma of 1.25 cft holds about one bag of cement by volume (0.0347 m³). For M20, use one bag, 1.5 boxes of sand and 3 boxes of aggregate.
- Allow for bulking. Damp sand swells, so a box of wet sand holds less sand than it looks. Buy a little extra sand in the monsoon.
- Cure for at least 7 days with ordinary Portland cement and at least 10 days with blended cement such as PPC or slag cement, as IS 456 requires (The Constructor's summary).
Common questions
How many bags of cement are needed for 1 cubic metre of M20 concrete?
About 8 bags. With the nominal mix 1:1.5:3 and the dry volume factor of 1.54, cement is 1.54 ÷ 5.5 = 0.28 m³, which is 403 kg or 8.06 bags of 50 kg. The same cubic metre needs about 0.42 m³ of sand and 0.84 m³ of 20 mm aggregate.
How many cement bags for a 1000 sq ft slab?
At 5 inches thick, a 1,000 sq ft slab holds about 417 cft or 11.8 m³ of concrete. In M20 that needs about 95 bags of cement, 175 cft of sand and 350 cft of aggregate. At 6 inches it is about 114 bags. Enter your own size above for the exact figure.
Why is the dry volume factor 1.54?
Loose cement, sand and aggregate have air gaps between the grains. When they are mixed with water and compacted, the fines fill those gaps and the volume shrinks. Site engineers add about 54% to the wet volume to cover this and a little wastage. It is a site rule used by Brick&Bolt and The Constructor, not a clause in IS 456.
Can I use 1:1:2 for M25 concrete?
IS 456 allows nominal mixes only up to M20. For M25 and higher, the code expects a design mix worked out from trial batches, or ready-mix concrete from a plant that tests its cubes. 1:1:2 is a site rule of thumb that may or may not reach 25 N/mm². Ask your structural engineer before using it.
How much water is needed for one bag of cement?
At a water–cement ratio of 0.5, one 50 kg bag needs 25 litres of water. IS 456 Table 9 allows at most 30 litres per bag for M20, 32 for M15 and 34 for M10. Adding more water to make the mix flow easily weakens the concrete.
What is a brass of sand?
A brass is 100 cubic feet, about 2.83 m³. It is a common unit for sand and aggregate in western India. In Surat, dealers more often quote per tonne, so the calculator shows m³, cft, brass and tonnes.
Sources
- IS 456:2000 Plain and reinforced concrete, code of practice (BIS): clause 9.3 and Table 9 nominal mix, Table 5
- IS 875 (Part 1):1987 Unit weights of building materials (cement 1,440 kg/m³, sand 1,540 to 1,600, stone 1,600 to 1,870)
- Brick&Bolt: how to calculate cement, sand and aggregates (dry factor 1.54, slab and PCC worked examples, modified June 2026)
- The Constructor: cement bags and sand for 1 m³ of M20 (worked example)
- Construction Civil Engineering: quantity of cement, sand and aggregate in an RCC slab (worked example)
- The Constructor: types of concrete mix and nominal mix ratios M5 to M25
- UltraTech Cement: what is concrete mix ratio (M25 as design mix)
- The Constructor: minimum curing period of concrete as per IS 456
- Careers360: 1 brass = 100 cft = 2.83 m³
- InfraLens: Surat cement prices per bag (updated 22 May 2026)
- InfraLens: Surat material prices, sand and aggregate per tonne (updated 22 May 2026)
- Construction World: cement prices rise ₹7 per bag in September 2026 (1 October 2026)
- IndiaMART: river sand prices in Surat (listings seen 24 November 2026)
- IndiaMART: construction aggregate prices in Surat (listings seen 24 November 2026)
- Gujarat Samachar: Gujarat doubles royalty on sand, gravel and clay (2 July 2025)